In June 2021, commissioning was completed and the first group of sand traps (4 units) was put into operation after reconstruction.
All reconstruction work was carried out in the normal mode, in accordance with the established schedule for the implementation of the project “Technical re-equipment of production facilities of JSC” GSR “Vodokanal”.
The performed work on the reconstruction of sand traps became another stage in improving the reliability of the CSP of GSR Vodokanal JSC, while ensuring compliance with strict environmental requirements for the safe operation of treatment facilities provided for by the legislation of the Russian Federation.