Project “Technical re-equipment of production facilities of JSC “GSR Vodokanal”:
Stage №1 – Construction of a sludge dewatering station – design and working documentation is being developed;
Stage №2 – Reconstruction of the system for treating industrial and storm water with the replacement of sand traps and reconstruction of radial sedimentation tanks – the development of working documentation is being completed, equipment is being supplied and preparations are underway for the start of construction and installation work;
Stage №3 – Construction of the wastewater return system – the development of working documentation has been completed, the manufacture and supply of equipment is in progress;
Stage №4 – Reconstruction of the sewerage network – design and working documentation is being developed, work has begun on the rehabilitation of three sections of pipelines, 280, 55 and 120 meters long.
Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...
Dear Colleagues! Today we celebrate a great memorable day - Victory Day! On this holiday, we are ...
Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...