Project “Modernization of the heat supply system of JSC “GSR CHPP” 3rd quarter of 2019

September 15, 2019
15.09.2019
  • Readiness for operation of collectors of direct network water and return network water in the area of boilers 7, 8 VK-2;
  • The installation of pipelines, fittings and pumps of the VK-2 silicate plant was completed;
  • The installation of thermal insulation of the thermal mechanical system VK-2 was completed;
  • Laying and flushing of the reserve water supply pipeline in VK-2 is completed