As of August 31, 2011, the following works were completed at the construction site of the CHP CCGT “GSR Energo”:
As part of the implementation of the project for a 110 kV double-circuit power transmission line, an agreement was received with the Department of Underground Structures of the Committee for Urban Planning and Architecture of the Government of St. Petersburg on the layout of supports along the route of the projected double-circuit 110 kV overhead line for the designed CHP CCGT “GSR Energo”.
Currently, the following works are being carried out at the construction site of the CHP CCGT “GSR Energo”:
The main equipment is manufactured in accordance with the schedule:
In accordance with the Project Quality Assurance Program, from September 01-05, 2011, inspections of the gas turbine rotor balancing were carried out, as well as inspections of the manufacture of section headers and the frame of the waste heat boiler.
Contracts for the supply of the following equipment have been concluded:
Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...
Dear Colleagues! Today we celebrate a great memorable day - Victory Day! On this holiday, we are ...
Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...