The work is being carried out in accordance with the project schedule.
Key milestones:
1. 26.04.2011 at the construction site of the CCGT CHPP, the first pile was driven under the foundation of the Main Building.
2. On-site preparatory work completed.
3. The pile field has been completed.
4. Work is underway on the installation of grillages.
5. Manufactured and ready for shipment of metal structures of the Main Building
6. The production of equipment continues: