Construction progress as of May 7, 2013

May 7, 2013
07.05.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 25.04.2013 to 07.05.2013:

  1. The installation was completed and the gas pipeline was purged in the section from Finlyandskaya St. to the construction site of the CCGT CHPP;
  2. The installation of the GTU emergency oil drain line was completed. The gas turbine oil system is flushed;
    Installation of demineralized water storage tanks 630 m 3 with drain and overflow pipelines and normal addition pipelines was completed;
  3. Completed installation of DCS. An autonomous commissioning of the DKS is underway;
  4. Completed installation of CNS pumps;
  5. The installation of the collective screen of the control room has been completed;

Other news

May 9, 2023

Congratulations on Victory Day

Dear Colleagues!   Today we celebrate a great memorable day - Victory Day! On this holida...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...

April 26, 2023

Hot water quality improvement plan 2023

Plan of measures to improve the quality of hot water supply from heat sources of GSR Energy CCGT-TPP...