Construction progress as of September 30, 2013

September 30, 2013
30.09.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from September 23, 2013 to September 30, 2013:

28.09.2013 16:50 synchronization and connection to the network was made, N= 8.4 MW. within 2 hours.

29.09.2013, the conservation of the boiler was completed.

28.09.2013 Successfully completed electrical testing of GTU and BTSN