Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from September 23, 2013 to September 30, 2013:
28.09.2013 16:50 synchronization and connection to the network was made, N= 8.4 MW. within 2 hours.
29.09.2013, the conservation of the boiler was completed.
28.09.2013 Successfully completed electrical testing of GTU and BTSN