Construction progress as of May 30, 2013

May 30, 2013
30.05.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 21.04.2013 to 30.05.2013:

  1. Thermal insulation of washing water tanks V 200 cu. m.
  2. Mounted RASTM PTU.
  3. The installation of the MK overpass from the GC to the switchgear of 0.4 cooling towers and from the switchgear of 0.4 cooling towers to the cooling tower was completed.
  4. Voltage is applied to RUSN 6/0.4 PNS.
  5. Flushing started.
  6. A deluge fire extinguishing system was tested in the area of the OUT.
  7. Completed work on the installation of industrial sewage short circuit.

Other news

January 6, 2025

С Рождеством Христовым !

Дорогие коллеги! Поздравляем вас с Рождеством Христовым! В этот прекрасный день желаем вам хор...

December 31, 2024

С Новым 2025 годом!

Дорогие коллеги! Поздравляем вас с наступающим Новым 2025 годом! Уходящий год был насыщен важн...

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...