Construction progress as of August 30, 2012

August 30, 2012
30.08.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 23.08.2012. to 30.08.2012

  1. Tests of SF6 circuit breakers KRUE-110kV were carried out.
  2. The installation of the foundations for the KVL-100kV entrances has been completed.
  3. Installation of the frame of the ventilation cooling tower has begun.
  4. We started laying brickwork for the walls of the PNS building.
  5. The installation of the M/C off-site overpass of process pipelines has begun.