Construction progress as of November 29, 2012

November 29, 2012
29.11.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from November 23, 2012 to November 29, 2012:

  1. Completed hydraulic test of the 1st bowl of the cooling tower.
  2. The construction of the foundations of the external overpass of technological pipelines in axes 23 – 72 was completed.
  3. The installation of gas pipelines on the on-site overpass of technological pipelines has begun.
  4. The installation of foundations for switchgear-0.4 kV cooling towers has been completed.

Other news

May 9, 2023

Congratulations on Victory Day

Dear Colleagues!   Today we celebrate a great memorable day - Victory Day! On this holida...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...

April 26, 2023

Hot water quality improvement plan 2023

Plan of measures to improve the quality of hot water supply from heat sources of GSR Energy CCGT-TPP...