Construction progress as of November 29, 2012

November 29, 2012
29.11.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from November 23, 2012 to November 29, 2012:

  1. Completed hydraulic test of the 1st bowl of the cooling tower.
  2. The construction of the foundations of the external overpass of technological pipelines in axes 23 – 72 was completed.
  3. The installation of gas pipelines on the on-site overpass of technological pipelines has begun.
  4. The installation of foundations for switchgear-0.4 kV cooling towers has been completed.

Other news

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...

May 9, 2023

Congratulations on Victory Day

Dear Colleagues! Today we celebrate a great memorable day - Victory Day! On this holiday, we are ...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...