Construction progress as of March 28, 2013

March 28, 2013
28.03.2013

Events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 22.03.2013 to 28.03.201Z:

  1. The tank of average wastewater with a volume of 200 cubic meters was assembled. m.;
  2. Laying of pressure pipeline network for drainage water K13N was completed;
  3. Laying of a section of the pressure network of oily effluents from the GTU to the GTU turbine oil emergency drain tank was completed;
  4. The installation of electrical equipment at the switchgear 0.4kV cooling towers has begun;