Construction progress as of September 27, 2012

September 27, 2012
27.09.2012

Information about the events that occurred at the construction site of the CHP CCGT “GSR Energo” in the period from 20.09.2012. to 27.09.2012:

The chimney of the waste heat boiler was installed;
Steam turbine anchors grouted;
Preparations for repeated hydraulic testing of the fan cooling tower pool have been completed.