Construction progress as of July 26, 2012

July 26, 2012
26.07.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 19.07.2012. to 26.07.2012:

1. The device of the foundations of the cable overpass from the main building to the RU-0.4kv gradirni of the i-th line was completed;

2. The foundations of the on-site overpass of technological pipelines up to axis 7 of the main building were completed;

3. Installation of KU feed and recirculation pumps;