Construction progress as of April 25, 2013

April 25, 2013
25.04.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 19.04.2013 to 25.04.2013:

  1. The installation of metal structures was completed, a gas pipeline and a steam pipeline were installed on the off-site overpass of technological pipelines. The steam pipeline has been inserted into the existing network.
  2. Hydraulic tests of the raw water pipeline network were carried out. Water was supplied to the water treatment plant for commissioning.
  3. The foundations of the on-site overpass of technological pipelines were completed.
  4. Demineralized water tank No. 2 is prepared for hydraulic testing.
  5. Tanks of average drains were handed over for thermal insulation and anti-corrosion protection.
  6. Cable routes GK – RU of cooling towers, CNS – cooling tower, 110 kV KVL entrances, handed over for cable installation.

Other news

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...

May 9, 2023

Congratulations on Victory Day

Dear Colleagues! Today we celebrate a great memorable day - Victory Day! On this holiday, we are ...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...