Construction progress as of July 24, 2013

July 24, 2013
24.07.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 07/08/2013 to 07/24/2013

  1. The launch operations of the DKS have been completed. Provided access to the operating mode.
  2. Test operations are being carried out on the gas turbine for idle start.
  3. The waste heat boiler is being prepared for hydraulic testing.
  4. Fencing of the BCP and BCS was completed.
  5. The external on-site networks of the fire-fighting water supply B2 were commissioned.
  6. Presented for delivery to the working commission is the installation of switchgear equipment.
  7. The installation of an open installation of transformers was submitted for delivery to the working commission.
  8. Two power transmission lines of 110 kV power transmission lines for 28 and 29 cells were submitted for delivery to the working commission.
  9. Conductors with cast insulation were submitted for delivery to the working commission.
  10. The structure of the on-site pipeline rack was commissioned.

Other news

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...

May 9, 2023

Congratulations on Victory Day

Dear Colleagues! Today we celebrate a great memorable day - Victory Day! On this holiday, we are ...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...