Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 07/08/2013 to 07/24/2013
- The launch operations of the DKS have been completed. Provided access to the operating mode.
- Test operations are being carried out on the gas turbine for idle start.
- The waste heat boiler is being prepared for hydraulic testing.
- Fencing of the BCP and BCS was completed.
- The external on-site networks of the fire-fighting water supply B2 were commissioned.
- Presented for delivery to the working commission is the installation of switchgear equipment.
- The installation of an open installation of transformers was submitted for delivery to the working commission.
- Two power transmission lines of 110 kV power transmission lines for 28 and 29 cells were submitted for delivery to the working commission.
- Conductors with cast insulation were submitted for delivery to the working commission.
- The structure of the on-site pipeline rack was commissioned.