Construction progress as of August 23, 2012

August 23, 2012
23.08.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 17.08.2012. to 23.08.2012

  1. Cable ties are being installed in the 110 kV switchgear building and cable ties are being installed in the GTU department.
  2. The installation of pipelines on the on-site overpass of technological pipelines has begun.
  3. The installation of bored piles on the off-site overpass of technological pipelines was completed.