Construction progress as of February 22, 2013

February 22, 2013
22.02.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 08.02.2013 to 21.02.2013:

  1. Completed installation of PPG
  2. The installation of the gas machine has been completed and the hydrotesting of the pipelines of the gas machine has been completed
  3. Completed installation of the second tank of demineralized water
  4. Installation of the SVEM high-voltage cable between supports 10 and 11 is completed
  5. The installation of the SVEM high-voltage cable from pylon 15 to 110kV switchgear has been completed

Other news

May 9, 2023

Congratulations on Victory Day

Dear Colleagues!   Today we celebrate a great memorable day - Victory Day! On this holida...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...

April 26, 2023

Hot water quality improvement plan 2023

Plan of measures to improve the quality of hot water supply from heat sources of GSR Energy CCGT-TPP...