Construction progress as of May 21, 2013

May 21, 2013
21.05.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 14.04.2013 to 21.05.2013:

  1. Flushing and hydraulic testing of fire extinguishing systems of the oil facilities of the Group of Companies, fire extinguishing systems of cable rooms of the Group of Companies, fire extinguishing systems of the OUT, fire-fighting external water supply are underway.
  2. Demineralized water storage tanks are being filled (hydraulic tests).
  3. The installation of gas pipelines from the BCP to the BCS and DF is nearing completion.
  4. WKO pipelines are being installed at the booster compressor station and in the main gas pipeline.
  5. The installation of pipelines of the GTU anti-icing system (piping of the WKO pumps, a membrane tank) is nearing completion.
  6. Acid washing of oil pipelines of industrial facilities is underway.
  7. Flushing of the GTU oil supply system continues.
  8. Circular water conduits and a ball cleaning system have been installed, drainage is being installed.
  9. The tie-in of the Du530 gas pipeline into the existing underground gas pipeline at st. Finnish

Other news

May 9, 2023

Congratulations on Victory Day

Dear Colleagues!   Today we celebrate a great memorable day - Victory Day! On this holida...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...

April 26, 2023

Hot water quality improvement plan 2023

Plan of measures to improve the quality of hot water supply from heat sources of GSR Energy CCGT-TPP...