Construction progress as of September 20, 2012

September 20, 2012
20.09.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 13.09.2012. to 20.09.2012:

  1. Concreting of the 1st tier of the walls of the storage tank was completed;
  2. Bricklaying and installation of the 110 kV KRUE staircase was completed;
  3. Sheet piling of the RASTM pit (transformer oil emergency drain tank) was completed;
  4. The brickwork of the GK basement has been completed;
  5. Alignment completed and steam turbine commissioned for grouting anchors;

Other news

May 9, 2023

Congratulations on Victory Day

Dear Colleagues!   Today we celebrate a great memorable day - Victory Day! On this holida...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...

April 26, 2023

Hot water quality improvement plan 2023

Plan of measures to improve the quality of hot water supply from heat sources of GSR Energy CCGT-TPP...