Construction progress as of September 20, 2012

September 20, 2012
20.09.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 13.09.2012. to 20.09.2012:

  1. Concreting of the 1st tier of the walls of the storage tank was completed;
  2. Bricklaying and installation of the 110 kV KRUE staircase was completed;
  3. Sheet piling of the RASTM pit (transformer oil emergency drain tank) was completed;
  4. The brickwork of the GK basement has been completed;
  5. Alignment completed and steam turbine commissioned for grouting anchors;