Construction progress as of June 20, 2013

June 20, 2013
20.06.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 04.06.2013 to 20.06.2013

  1. The gas pipeline is assembled into a production scheme and prepared for the final testing and acceptance of gas.
  2. Hydraulic tests of the pipelines of the fire system and the cooling system of the booster compressor station are being carried out.
  3. The pipeline of the closed cooling circuit from the main building to the Palace of Culture was put into operation. Within the Civil Code for rent on 21.06.13.
  4. The thermal insulation of the steam pipelines of the external ETT has been completed.
  5. Water-chemical cleaning of the waste heat boiler was carried out and passivation started.
  6. Anti-corrosion protection and thermal insulation of steam pipelines for auxiliary needs with a pressure of 0.7 MPa and 1.3 MPa and a steam pipeline for heating the drums of a high and low pressure boiler was carried out.
  7. The work on the roof of the main building has been completed.

Other news

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...

May 9, 2023

Congratulations on Victory Day

Dear Colleagues! Today we celebrate a great memorable day - Victory Day! On this holiday, we are ...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...