Construction progress as of July 19, 2012

July 19, 2012
19.07.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 12.07.2012. to 19.07.2012:

1. Concreting of the walls of the fan cooling tower pool was completed;

2. Completed the immersion of the sheet piling of the accumulation tank;

3. Installation of the chimney of the KU up to elevation +32.500 was completed;

4. Installed diffuser from GTU to CHP (without TI);

5. The steam turbine rotor was depreserved;

6. Completed the revision of the flow path of the steam turbine;

7. The first alignment of the turbo group (generator, power gearbox and gas turbine) was completed.

Other news

January 6, 2025

С Рождеством Христовым !

Дорогие коллеги! Поздравляем вас с Рождеством Христовым! В этот прекрасный день желаем вам хор...

December 31, 2024

С Новым 2025 годом!

Дорогие коллеги! Поздравляем вас с наступающим Новым 2025 годом! Уходящий год был насыщен важн...

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...