Construction progress as of April 18, 2013

April 18, 2013
18.04.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 04/12/2013 to 04/18/2013:

  1. Completed installation of auxiliary equipment of vocational schools.
  2. The installation of foundations for the on-site overpass of technological pipes was completed.
  3. Raw water pipelines are being flushed to supply TLU equipment for flushing. The raw water system is prepared for water supply to the WLU.
  4. Hydraulic tests and purge of the CO2 fire extinguishing system were carried out. The equipment is permanently connected
  5. GTU oil pumps are being scrolled.

Other news

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...

May 9, 2023

Congratulations on Victory Day

Dear Colleagues! Today we celebrate a great memorable day - Victory Day! On this holiday, we are ...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...