Construction progress as of October 17, 2013

October 17, 2013
17.10.2013

Work progress status as of 09-00 10/17/2013

Steam turbine

  1. Successfully completed work on setting the turbine rotor to barring.
  2. Completed work on a trial set of vacuum condenser PT – no remarks
  3. (P= – 68 kPa).
  4. The steam pipeline from the old part of the BCHP-2 to the CCGT CHPP was turned on.
  5. The Auxiliary Reducing Cooling Unit (ROU SN) and the Auxiliary Steam Collector (KSN) were put into operation.