Construction progress as of August 16, 2012

August 16, 2012
16.08.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 09.08.2012. to 16.08.2012

  1. The installation of the wall fencing of the main building building has been completed.
  2. The installation of technological pipelines on the overpass has begun.
  3. The DC room is prepared for equipment installation.
  4. The installation of electrical equipment in the KRU 6kV has begun.
  5. The installation of electrical equipment in the 110 kV switchgear was completed