Construction progress as of September 14, 2012

September 14, 2012
14.09.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 09/06/2012 to 09/13/2012:

  1. The reinforced concrete bottom of the storage tank was completed, the installation of the frame and wall formwork began;
  2. The immersion of the RASTM sheet piling (transformer oil emergency drain tank) was completed;
  3. The installation of SOPT at elevation +8,700 has begun;
  4. Completed pre-assembly of the chimney up to elevation +60,000;
  5. Inserts No. 1, No. 2 were made into the heating network of the operating boiler house;
  6. We proceeded with the installation of pipelines of the main condensate on the pipe stack.

Other news

January 6, 2025

С Рождеством Христовым !

Дорогие коллеги! Поздравляем вас с Рождеством Христовым! В этот прекрасный день желаем вам хор...

December 31, 2024

С Новым 2025 годом!

Дорогие коллеги! Поздравляем вас с наступающим Новым 2025 годом! Уходящий год был насыщен важн...

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...