Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 26.04.2013 to 14.05.2013:
- Steam piping completed. Preparations are underway for purging and hydraulic testing.
- The gas pipeline was tested and purged from the underground tie-in into the existing network at support 82 to the BCP. The act of the State Commission was signed.
- The installation of the gas pipeline from the BCS to the duplex filters has begun.
- The metal structures of the cable route from the GC to the switchgear of 0.4 kV cooling towers were mounted.
- The foundations of the cable trestle from the switchgear switchgear 0.4 kV of the cooling towers to the cooling tower were completed.
- The foundations for the noise-insulating partitions of the OUT have been completed.
- GTU oil system flushing started.
- Improvement of the territory and the construction of the road surface in the 110kV switchgear area have begun. – Pumping station for household and fire water supply – PPG.
- Completed installation of PNS equipment.
- The equipment of pumps for normal and emergency addition was installed.
- The piping of the desalinated water tanks has been completed. A hydraulic test is underway.
- A temporary diagram of the nozzles for acid washing of the CU was mounted.
- Acid flushing of the oil pipelines of the PTU is being carried out.
- Commissioning and commissioning of reverse osmosis systems are being carried out. Received demineralized water.