Construction progress as of March 14, 2013

March 14, 2013
14.03.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 03/08/2013 to 03/14/2013:

  1. At the entrance of the 110 kV switchgear (support No. 15), the installation of 6 couplings for connecting the overhead line and the cable line has been completed.
  2. The installation of metal structures and cable structures of the overpass PNS – KRUE 110 kV was completed.