Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 06/07/2013 to 06/13/2013.
- Hydraulic testing of the gas pipeline was carried out and it was purged in the section from the BCP to the BCS.
- The section of the gas pipeline from the BCS to the duplex filter module is being purged.
- The low-pressure steam pipeline from the tie-in unit to the main building was commissioned.
- The steam pipeline for own needs in the main building was put into operation.
- The steam pipeline is prepared for purging with a pressure of 1.3 MPa.
- A hydraulic test of the steam collector with a pressure of 0.7 MPa is carried out.
- High-speed flushing of the waste heat boiler with the addition of NH3 is underway.
- The flushing of the oil system of the gas machine generator is being completed (the 4th circuit is being washed).
- An act of commissioning of 2 CNS pumps was signed.