Construction progress as of December 14, 2012

December 14, 2012
14.12.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 06.12.2012 to 13.12.2012:

  1. Started construction and installation work on the installation of oily wastewater treatment facilities;
  2. The installation of current conductors in the section from KRU-b kV to auxiliary transformers has begun;
  3. The installation of live steam pipeline Ø 273×26 from the waste heat boiler to the stop valve of the steam turbine has been completed;

Other news

December 31, 2023

Happy New Year 2024

Dear Colleagues ! Please accept our heartfelt congratulations on the coming New Year 2024! The Ne...

May 9, 2023

Congratulations on Victory Day

Dear Colleagues! Today we celebrate a great memorable day - Victory Day! On this holiday, we are ...

May 1, 2023

Happy May Day!

Dear Colleagues, Congratulations on May 1st! This day is the main holiday of spring and symboliz...