Construction progress as of October 12, 2012

October 12, 2012
12.10.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 05.10.2012. to 11.10.2012

  1. The hydraulic test of the fan cooling tower has been completed.
  2. The thermal contour of the building of the main building is closed.
  3. We started repairing the existing technological overpass.