Construction progress as of July 12, 2012

July 12, 2012
12.07.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 06.07.2012. to 12.07.2012:

  1. OUT transformers are installed on the foundations.
  2. The 110 kV switchgear room was handed over for the installation of 110 kV power cells.
  3. Completion of the power floors in the Main building