Construction progress as of April 11, 2013

April 11, 2013
11.04.2013

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 04/05/2013 to 04/11/2013:

  1. The installation of all foundations for off-site overpasses of technological pipelines was completed and the installation of metal structures for the new overpass was completed.
  2. The installation of the second tank of average wastewater with a volume of 200 cubic meters has been completed.