Construction progress as of September 06, 2012

September 6, 2012
06.09.2012

Information about the events that took place at the construction site of the CHP CCGT “GSR Energo” in the period from 30.08.2012. to 06.09.2012

  1. 110kV switchgear high voltage test checked.
  2. Concrete work has been completed on the installation of a ventilation cooling tower basin and a circulation pumping station.
  3. Concrete work on the installation of foundations for an open installation of transformers has been completed.
  4. Reinforcement of the bottom of the accumulation reserve has begun.