GE gas turbine warranty testing completed. All characteristics, according to the supply contract, are confirmed.
The final inspection of the construction of power unit No. 1 of the SZU Rostekhnadzor was completed, a conclusion on compliance (AIA) was received.
Operational and commissioning tests of the unit as a whole are being carried out, according to the results, a report and regime cards for operational personnel will be issued.
A package of documents is being prepared for obtaining a commissioning permit from the state construction supervision.
Documents have been submitted for the registration of a hazardous production facility (HPO).