On November 19, 2013, a comprehensive testing (CT) of the equipment of the power unit No. 1 of CJSC GSR CHPP was carried out.
At present, comments are being eliminated after passing the KO, preparations are underway for the passage of warranty and mode-adjustment tests.
At the same time, a package of documents is being prepared for the registration of the entire facility with the Rostekhnadzor authorities.