July, 2013

  1. Start of booster compressor station engine is carried out.
  2. Gas turbine-to-gearbox centering adjustment is executed. Gearbox-to-generator centering adjustment is started.
  3. Booster compressor station startup is finished. Operating mode is achieved.
  4. Assembling of switchgear equipment is submitted to working commission.
  5. Transformers assembling is submitted to working commission.
  6. Idle start of gas turbine is carried out.
  7. Hydrostatic tests of exhaust-heat boiler are carried out