June, 2013

  1. Gas pipeline is assembled and prepared for final test and gas feeding.
  2. The water-chemical washing of exhaust-heat boiler is carried out and passivation is begun.
  3. Hydrostatic tests of gas pipeline are carried out. Gas pipeline purge from gas preparation module to booster compressor station is executed.
  4. Hydrostatic tests 0,7 MPa of steam header are made.
  5. High-speed washing of exhaust-heat boiler with addition of NH3 is conducted.
  6. Operational Acceptance Certificate of two pumps of circulating pumphouse is signed