About usGSR Energy is an investment group that focuses on
investments in the newest technologies of the development of city
infrastructure, in particular thermal and electrical energy production, supply,
and sales, water supply and disposal systems, and the development of housing
and communal services. The company has already implemented projects the
investment volume of which was more than 10 billion roubles. To the moment, the
following projects have been implemented: 2014 – putting into operation new combined cycle
gas-turbine thermal power plant (CCGT-TPP) with the combined electrical and thermal
energy production of 110 MW / 77 Gcal/h, and capacity factor of more
than 80%. In-parallel withdrawal of three old boilers with the total output of
150 Gcal/h; 2017 – the withdrawal of old Central Boiler Station
with the output of 70 Gcal/h; 2019 – putting into operation new Steam Boiler with
the steam output of 48 t/h. The withdrawal of old Block-Type TPP No. 2
with the thermal energy output of 322 Gcal/h and electrical energy output
of 20 MW;
2020 – the modernization of the VK-2 water boiler
station with the output of 400 Gcal/h. |
|